A Big Workday
A lot of things happened as this massive team began its work today. We got the batteries fully connected inside the PowerPac, we also fired up our small inverters that will eventually provide power for all the communication equipment. We also began work on the Solar Inverters on the outside of the PowerPac. We began running conduits in the open trench headed for the Hospital Utility Room where our centralized panels will be located. One funny thing happened as the guys were putting conduits in the trench. A roll of duct tape got dropped into the open sewer trench and rolled down the hill right past the PowerPac. No one reached into the trench to retrieve it while it rolled past... If things go well tomorrow, we may turn the PowerPac on using the incoming utility power, so that we can begin testing the system. Solar panels are being installed and by sometime next week they should be providing power from the sun to the PowerPac. ...